Tanunda Recreation Park Clubrooms and Changerooms
- Address
- Elizabeth Street, Tanunda (view map)
- Status
- Completed
- Anticipated completion date
- 22 December 2023
- Budget
- $6,494,980
- Partners
- Kennett Builders
Grant: $1,500,000, Council: $4,994,980, Total Project Value: $6,494,980
This project will develop truly regional, multi-use, gender-neutral, transformational infrastructure that delivers shared football, cricket, netball, tennis and community sports facilities. Facilities will meet contemporary standards and provide high quality, inclusive, accessible infrastructure to support participation in grassroots competition.
- shared clubrooms with 280 capacity seating and public lounge
- six gender-neutral changerooms plus umpire rooms
- gender neutral toilets for sporting and public use
- spectator viewing to oval and courts with connecting internal breezeway
- office and storage spaces
- expanded use of existing Tanunda Show Hall commercial kitchen
- civil and landscaping improvements
The redevelopment is part of a shared vision with SACA and SANFL to develop the Barossa as the best regional sports event tourism destination for AFL and cricket in South Australia.
Opening Event
March 2024
Clubrooms now complete
September 2023
Bar Area
September 2023
Main Entrance
September 2023
Changerooms are Complete
August 2023
Bar Area and Spectator Viewing
June 2023
Internal walls and ceiling
June 2023
Windows
May 2023
New Verandah for Changerooms
April 2023
Feature Wall Complete
April 2023
Duct Work
March 2023
Structural Steel Complete
March 2023
Structural Steel
February 2023
Canteen External Walls
February 2023
Concrete Pour
January 2023
Concrete Preparations
December 2022
Demolition of existing clubrooms
November 2022
Sod turning
November 2022
Contract Awarded
September 2022
Tender
June 2022
Detailed design
May 2022
Grant funding received
February 2022
Concept design
July 2021
Master Plan
May 2017
Community Consultation
January 2017
Initial Concept Design
February 2016
Costs
Total project costs of $6,494,980 through the following funding:
- The Barossa Council: $4,994,980
- Grant: $1,500,000
Contractors
- Kennett Builders have been awarded head contract for the clubrooms and changerooms on 9 May 2022